News

Preferred Conveyance Route Selected for Comox Valley Sewer Service

24 February 2021

On February 23, 2021, the Comox Valley Sewage Commission approved a plan to upgrade the pipes and pump stations that move wastewater from Courtenay, Comox and the K’ómoks First Nation to the sewage treatment plant.

Key features of the selected option are:

  • A mix of tunneled sections (under Comox Ave. and Lazo hills) with traditional ‘cut-and-cover’ trenched installation. The tunneling will reduce the construction impact and operational pressure on the system.
  • Work to be undertaken as one phase, rather than separated into two phases divided by up to 15-20 years, to reduce risk posed by the estuary’s foreshore forcemain.

The option is anticipated to cost $73 million, paid for by $21 million in reserves, and $52 million in long-term borrowing. The cost per household is estimated at $150/per year for 30 years. Read the press release here.