News

Project Update: Balmoral Avenue (Pritchard Rd to Torrence Rd)

17 October 2024

Construction for the new sewer forcemain is almost complete on Balmoral Avenue. The last element to complete are the connections to the air management points.

Work continues for the Town of Comox infrastructure upgrades. Crews are currently working on completing storm drains and preparing the curb and road for paving.

Wacor will be delivering letters to properties impacted by curb forming and paving with specific dates and timelines. We would like to extend our sincerest thanks to residents on Balmoral Avenue. We appreciate the cooperation and support you’ve extended as we’ve worked to complete this important project.

Here is an updated timeline of construction you can expect to see on Balmoral Avenue: