Project Update: Balmoral Avenue (Pritchard Rd to Donovan Dr)

1 November 2024

Work on the Balmoral Avenue Improvements Project and the Comox Valley Sewer Conveyance Project are nearing completion on Balmoral Avenue.

A tentative paving date for Balmoral Avenue, Pritchard Road to Donovan Drive has been identified for Monday, November 4, 2024. If weather permits paving of both the north and south side of the road will proceed. Crews will also use this time to complete work on curbs, sidewalks and driveways.

Please expect Balmoral Avenue to be closed Pritchard Road to Donovan Drive. There will also be intermittent sidewalk closures.

Please anticipate delays and follow all signs and directions from traffic control personnel.

If there is inclement weather, work will be postponed and another date will be selected to complete the work.

We thank our community for their continued support as we work to complete these important infrastructure projects.